Week Eleven of the Two Storey Side Extension Project in Bexley, Kent |
Follow the daily progress during the eleventh week of S M Berry's twelve week extension project
Last week Scott Berry and his team started the second fix carpentry which they will complete this week along with any snagging that needs to be done. Scott is very pleased with the progress that has been made by the team as they are well ahead of schedule and will definitely complete on time.
Follow S M Berry Building Contractors Ltd progress this week by clicking on the tabs below....
Today the floor was screeded on the ground floor....
The architraves, door linings, skirtings, window boards and doors were fitted to the ground floor...
Today Scott and his team finished the front and rear soakaways and the small retaining wall around the extension.
|
|
|
|
Case Study II - Extension
|
S M BERRY BUILDING
- Extensions
- Loft / Garage
Conversions
- New Builds
- Renovations
- Refurbishments
- Plastering
- Rendering
- Conservatories
- Internal /
External Decoration
- Plumbing
- Electrics
- Carpentry
- Roofing
- Gutter & Fascias
- Kitchen
Installations
- Bathroom
Installations
- Paving
- Driveways
- Decking
- Garden Walls
- Fencing
|

|